Project report · Every two months

Project report: 25 October 2026

Drikung Kagyu Monastic School. Phase 1A dormitory and Phase 1B classrooms.

Report date
25 October 2026
Period covered
28 August 2026 to 25 October 2026
Prepared by
Tenzin Dawa, General Secretary
Financial figures checked to
25 October 2026

1Project summary

The construction of the monastery’s new dormitory and classrooms began on 28 August 2026. The project aims to improve residential and educational facilities for the young monks. Fundraising and construction work are ongoing.

2Construction progress

AreaCurrent statusWork completed this period
Phase 1A dormitoryUnderwayConstruction of structural pillars, walls and window frames. Pouring of the roof slab (lenter) has started.
Phase 1B classroomsNot startedNot started yet. The site is being used as the current dormitory.

Delays or changes: none.

3Next two months

Planned work
Building of the roof slab and curing (hardening) it with water.
Expected milestone
Roof slab structure built and cured, with related works, expected to be complete by 25 December 2026.

4Fundraising position

Approved Phase 1 goalINR 1,27,40,464
Phase 1AINR 70,57,556
Phase 1BINR 56,82,908
Total contributions toward the goalINR 26,88,938
Still neededINR 1,00,51,526

5Financial summary in INR

Movement during this period

ItemAmount (INR)
Opening project funds26,64,272
Add donations received through Ketto0
Add other project receipts0
Less platform and payment fees0
Less donor refunds0
Less project expenditure paid20,00,000
Closing project funds6,64,272

Where closing funds are held

Project bank and cash balancesINR 6,64,272
Held by Ketto and not yet settledINR 24,666

Spending by category

CategoryThis period (INR)To date (INR)
Materials and structural work19,27,13919,27,139
Labour and transport4,01,4004,01,400
Contractor or management allowanceNil (not invoiced yet)Nil (not invoiced yet)
Total project expenditure to date23,28,53923,28,539
Total paid to date20,00,00020,00,000
Unpaid invoices3,28,5393,28,539

Unpaid invoices or committed costs. To date, the organization has paid INR 20,00,000 (twenty lakh rupees) to the assigned contractor. Bills amounting to INR 23,28,539 (twenty-three lakh, twenty-eight thousand, five hundred and thirty-nine rupees) have been received for the project so far. The outstanding unpaid invoice amount is therefore INR 3,28,539 (three lakh, twenty-eight thousand, five hundred and thirty-nine rupees).

6Dated construction photographs

Right front of the monastery, with the new first-floor dormitory under construction above the ground floor
Site overview · 20 October 2026Right front of the monastery: the new first-floor dormitory being built. The ground floor is still used as the current dormitory.
View across the top of the new dormitory construction site toward the town and hills
Site overview · 20 October 2026Photo from the top of the new dormitory construction site.
The first-floor dormitory under construction, seen from the monastery courtyard
First-floor dormitory · 20 October 2026Daytime photo of the first-floor dormitory.
The ground floor that will become the classrooms, currently used as the dormitory
Ground-floor classroom area · 20 October 2026The ground floor is currently being used as the dormitory.

7Approval and publication

Construction reviewed by
Ven. Konchok Lekden
Finances reviewed by
Tenzin Yangdon
Approved for publication by
Sonam Choedon
Next report due
25 December 2026
Contacts
Coordination: Tenzin Dawa Lhundup. Financial reporting: Tenzin Yangdon. Public enquiries: wtsl1971@gmail.com