Project accountability

Project reports

Follow the dormitory and classroom project through construction updates, dated photographs and financial summaries.

Report archive

Construction and financial reports are published here every two months, with photographs and a clear account of how contributions are used.

First project report

25 October 2026

Covers 28 August to 25 October 2026: construction progress, the next two months, fundraising position, a financial summary and dated photographs.

Invoiced to date
INR 23,28,539
Paid to contractor
INR 20,00,000
Closing project funds
INR 6,64,272
Read the report

Next report due 25 December 2026.

Return to budget and transparency →